Contact   About Us
  Sustainablilty Site Map
  Press - News   Links
  Reference Data   Home
              Media              Contractor Opportunities   Pentagon Personnel           Other Visitors       

Wedge 2-5 home page

WEDGE 2 - 5

Wedges 2-5 is a phased design/build renovation of 4 million square feet of space in the Pentagon. The project brings all remaining un-renovated areas of the building into compliance with modern building, life safety, ADA and fire codes. Work includes removal of all hazardous materials, replacement of all building systems, addition of new elevators and escalators to improve vertical circulation, and installation of new security and telecommunications systems. Renovated spaces will be modern, efficient, and flexible. The project, underway since September 2001, is on an accelerated schedule for completion in December 2010, four years sooner than originally planned. During the past year, much has been accomplished on Wedges 2-5. Master plan design of Wedges 2- 5 is complete, as is core and shell design of the first two phases of Wedge 2. Tenant fitout design is well underway, and design of the third (and final) phase of Wedge 2 is in progress. Sustainable design measures have been integrated into the design. The Wedges 2-5 project is enrolled in the Leadership in Energy and Environmental Design (LEED) Existing Buildings Pilot Program, and is working to achieve a gold rating. Force protection initiatives prompted by the September 11, 2001 terrorist attack have been successfully incorporated into the design. These include increased blast resistance, improved fire protection/life safety, and inclusion of chemical, biological and radiological (CBR) protection. Construction is progressing well in all areas of the first two phases of Wedge 2, and is on track for completion in October 2003. Demolition and abatement was completed ahead of schedule in April 2002. Decommissioning of building mechanical, electrical and telecommunications systems was recently completed. Because of the age and poor documentation of existing systems, the decommissioning effort required detailed planning and careful execution. Work currently ongoing includes construction of new half-corridor bridges, installation of new elevators, and rapid build-back of tenant office spaces.

CHALLENGES
Key project challenges include integration of changing requirements (primarily telecommunications and force protection upgrades), tenant requirements gathering, and coordination of project turnover/tenant relocations. The September 11, 2001 terrorist attack caused the Renovation Program to reassess and upgrade project design criteria in many areas. Identification and implementation of the new criteria has been extremely challenging because design and construction had to proceed while studies were in development in order to meet the overall accelerated program schedule. Tenant requirements gathering has historically been a challenge for the Renovation Program and continues to be a challenge for Wedges 2-5, particularly for nontypical tenant spaces. Project turnover and tenant relocation to newly completed space is a complex effort. It must be carefully orchestrated to ensure a smooth transition for tenant missions and timely release of new areas for renovation.

MILESTONES
The renovation of Wedges 2-5 will be accomplished in four major increments (wedge by wedge), each of which has been sub-phased to accommodate the accelerated schedule. Wedge 2 has three sub-phases. The first two phases are under construction now and will be complete in October 2003, and the third phase will be complete in November 2005. Tenant relocation to newly renovated spaces will occur in phases, beginning in June 2003. The Wedge 2-5 project is also responsible for completing a building-wide pathway for a new telecommunications backbone. This task is dependent upon making final building-wide connections to the new Center Courtyard utility infrastructure. This coordinated effort will be complete by Summer 2003.

WHS web site